Number of ADUs Allowed in Bell

Number of ADUs Allowed in Bell

How many ADUs can you build in Bell?

In Bell you can build up to one ADU (either attached or detached) and one JADU on single-family property.

How many ADUs does Bell allow for multifamily properties?

Multifamily property owners in Bell may convertat least one ADU,and additional ADUs not to exceed a maximum number equal to 25% of the existing units out ofexisting uninhabitable space.Ergo:

 

  • From 2 to 7 units, you could convert existing uninhabitable space into one ADU
  • From 8 to 11 units up to 2 ADUs
  • From 12 to 15 units up to 3 ADUs
  • And so on.

 

No more thantwo detached ADUs may be constructed on a multifamily lot in Bell.

Bell ADU built by GO ADU Construction

ADU Bell – Size & Building Constraints

What size detached ADU can you build in Bell?

In Bell, the maximum size for a detached ADU is 1,200 square feet.

How big can an attached ADU be in Bell?

In Bell an attached ADU can be up to 1,200 square feet or 50% of the size of the main dwelling unit, whichever is smaller.

What is the height requirement for an ADU in Bell?
In the City of Los Angeles, converting existing structures into ADUs carries no height restriction. The height of new-construction ADUs must be less than 16 feet, although, in certain locations, new-construction or partially new-construction designs may include an ADU as tall as 25 feet. For multifamily properties where the existing structure is at least two stories high or if the property is located within a ½ mile walk of a public transit stop or station, an ADU can be up to 18 feet high.
Can you build a 2-story ADU in Bell?

An attached ADU may be two stories in Bell. However, due to height restrictions you cannot build a two-story detached ADU in Bell.

Can you stack detached ADUs on top of each other?

No, stacked ADUs (one ADU on each floor of a two-story structure) are not allowed in Bell.

Can you attach two ADUs to each other in Bell?

No, two ADUs attached together are not allowed in Bell.

Can you build an ADU with an attached JADU?

No, a JADU is defined as an ADU converted from existing space within the main structure of the primary dwelling unit. As such, it cannot be attached to an ADU.

Does Bell allow roof decks on ADUs?

Roof decks are not prohibited for ADUs in Bell. However, California building safety codes about roof deck safety railings apply, and the height of the railing applies to the total height of the building, so the whole structure including the railings must comply with ADU height requirements. California requires that deck rails be 36 inches high on residential dwellings, 42 inches high on multifamily dwellings.

What are the requirements for the exterior of the ADU?

The exterior of the ADU must align with the architectural and aesthetic style of the rest of the neighborhood, using similar materials and design elements to maintain consistency with the main dwelling unit and surrounding dwellings.

ADU interior in Bell

ADU Setbacks in Bell

What is the setback requirement for an ADU in Bell?

The City of Bell requires 4-foot rear and side setbacks for new-construction ADUs. ADUs converted from existing structures may be exempt.

What is the minimum distance the ADU must be from existing structures?

The City of Bell requires a minimum of 6 feet of separation between the new ADU and any other structures. ADUs converted from existing structures may be exempt.

Can you build an ADU in the front yard in Bell?

No, ADUs are not allowed in the front yard of residential property in Bell.

ADU Setbacks in Bell

Does Bell require in-person submission of plans for an ADU?

Yes, Bell requires in-person submission of plans to the Planning Devision.

Does Bell require a soils report for an ADU?

Bell may require a soils report for ADU permitting to make sure the soil can support the new structure, especially if the ADU will be located on a hillside, an area with significant grading, or if there are special foundation requirements.

What landscaping requirements apply to ADUs in Bell?

While not setting a percentage, Bell requires that property maintain “sufficient” open and permeable space on the lot.

What is the plan check process with Bell? How long does it take?

The plan check requires a review by the Planning Department and the Department of Building & Safety for zoning, building standards, and safety compliance. The process takes approximately 3-6 weeks.

Parking for Bell ADU

What is the parking requirement for an ADU in Bell?

Bell typically requires one additional parking spot per ADU be added to the property. However, if the property is located within a half-mile of a public transit stop, it may be exempt from this requirement. ADUs converted from an existing garage or carport are also exempt from this parking requirement, as are properties located within a designated historic district.

Where can a parking space be located?

If a parking space must be added, it can be included on the driveway or configured as tandem parking.

Backyard ADU in Bell

Additional Requirements in Bell

Am I required to install solar panels?

Per Title 24 of the California Energy Code, solar panels of appropriate size and capacity are mandatory on new-construction ADUs. ADUs built from converted existing structures are exempt, as may be ADUs located under significant shading. Smaller ADUs may be subject to reduced or modified solar panel requirements.

Am I required to put separate electric and water meters for the ADU?

An ADU is not required to have a separate water or electrical meter. You can opt for the ADU to share service with the main dwelling unit. However, you can request separate water or electrical meters from the City of Bell.

Does the ADU get its own address?

Bell does not automatically assign a new ADU its own address. However, it may assign the ADU a new address if it is intended for rental or independent occupancy. The ADU will usually get a “½” designation — for example, an ADU located behind 1234 Pine Street would have the address “1234½ Pine Street.”

What is LID (Low Impact Development)?

Low Impact Development (LID) is an approach to land development or redevelopment that seeks to preserve and conserve onsite water quality and natural features, with minimal detrimental effect to local waterways and ecosystems. Bell may require LID fees for larger ADUs.

Can I Airbnb my ADU? Use it as a short-term rental?

No, Bell doesnotallow residents to use an ADU as an Airbnb or short-term rental (30 days or less).

Will my ADU be rent-controlled?

Per the Costa-Hawkins Act of 1995, Bell does not impose rent control on dwellings constructed after February 1, 1995. This means most new-build ADUs are exempt. However, if the primary dwelling unit is subject to rent control, it might apply to the ADU as well.

Can I use gas appliances in my new ADU?

While encouraging the use of electric appliances for efficiency and sustainability, Bell does not prohibit gas appliances in new ADUs.

Am I required to put fire sprinklers in my ADU?

In Bell you are only required to install sprinklers in a new ADU if the primary dwelling unit has them as well. You may also be required to install them if the ADU is located within a special fire hazard zone.