Number of ADUs Allowed in Carson
- Maximum size: 1,200 sq ft (detached or attached, or 50% of the size of the main dwelling)
- Side/rear setbacks: 4 feet
- Two story: Yes, for both attached and detached ADUs
- Building separation: 6 feet
- Soils Report: Possibly, especially in areas with grading or on hillsides
- Building Verification Survey: Yes
- Coastal permit (in some areas): N/A
- Stormwater Mitigation: Yes
Number of ADUs Allowed in Carson
On single-family residential lots in Carson, you may buildone ADU, either attached or detached, on your property. You can also build up toone JADUinto the existing primary residence.
Multifamily property owners in Carson may convertat least one ADU, andadditional ADUs not to exceed a maximum number equal to 25% of the existing units out ofexisting uninhabitable space. Ergo:
- From 2 to 7 units, you could convert existing uninhabitable space intoone ADU
- From 8 to 11 units up to2 ADUs
- From 12 to 15 units up to3 ADUs
- And so on.
No more thantwo detached ADUs may be constructed on a multifamily lot in Carson.

ADU Carson – Size & Building Constraints
A detached ADU can be a maximum of 1,200 square feet in Carson, or up to 60% of the size of the main dwelling unit, whichever is smaller.
In Carson, an attached ADUs can be up to 50% of the existing living area of the main dwelling unit, to a maximum of 1,000 square feet.
In Carson, an ADU must be a maximum of 16 feet high unless granted a special exemption by the city.
Two-story ADUs can be permitted in Carson, but they must follow height requirements. Without a special exemption, ADUs are limited to 16 feet. 16 feet is usually too low for two-story buildings, which typically require at least 18 feet.
It is difficult to build “stacked” ADUs (a two-story structure with one ADU on each floor) in Carson. Residential property can only be permitted for one ADU, meaning a second ADU to stack on top of the first one will not be permitted. Multifamily property can be permitted for up to two detached ADUs, but the standard height limitation of 16 feet for detached ADUs usually makes a two-story structure infeasible.
Residential property can only be permitted for one ADU, so you will probably not be permitted for two ADUs, attached to each other or otherwise. However, multifamily property can be permitted for up to two detached ADUs, and itispossible to design those two ADUs to be attached to each other within one new structure.
No, a JADU is defined as a small ADU converted from existing space within the main structure of the primary dwelling unit. As such, it cannot be attached to an ADU.
Generally roof decks would be permitted on an ADU, but must meet the height restrictions for the zone. Roof decks cannot encroach into the required setbacks. As a rule of thumb, railings and access staircases above 42″ need to be included in height calculations.
Carson makes no mention of specific requirements for the exterior of the ADU. However, general guidance is that the exterior roofing, trim, walls, windows and the color palette of the ADU shall incorporate the same features as the primary dwelling unit.

ADU Setbacks in Carson
A detached ADU in Carson requires a minimum four-foot side and rear setback.
A detached ADU in Carson requires a minimum ten feet of separation from any existing structure.
ADUs can generally not be permitted in the front yard of a home in Carson.
ADU Setbacks in Carson
Yes, the City of Carson requires you submit your ADU plans in person to the Carson Planning Division.
Carson does not list a soils report among its required ADU submittal documents. The city's ADU application requires a completed ADU Plan Review Application, one electronic set of plans, and a signed and notarized covenant before approval is issued.
That said, the California Building Code can still trigger a soils or geotechnical report on a project-specific basis - typically when the work involves deep excavation, building on a slope, or construction near older structures. Confirm with Carson Building and Safety during plan check.
The City of Carson requires homes to maintain 50% of their front yards as green space, but since ADUs usually cannot be permitted for front yards, this doesn’t affect most ADU plans. Carson does not specify strict requirements for green space or permeable hardscapes in backyards, but residents are encouraged to mind green space and make a significant portion of any hardscapes permeable.
To start the plan check process, you’ll need to submit your ADU plans in-person to the city’s Planning Division.
The length of the plan check depends. It can take anywhere from 60 to 90 days to get your plans approved as they move from one department to the next. This can depend on how busy the city is, if your plans have any issues, and how many corrections you may have to make.
Parking for Carson ADU
Carson requires that you add one new parking space to your property per ADU. However, several exemptions have been put in place to make it easier to add an ADU. You need not add parking when any of the following apply:
- The ADU is located within one-half mile walking distance of public transit.
- The ADU is located within an architecturally and historically significant historic district.
- The ADU is part of the proposed or existing primary residence or an accessory structure.
- The ADU is built into an existing garage or carport.
- When on-street parking permits are required but not offered to the occupant of the accessory dwelling unit.
- When there is a car share vehicle located within one block of the accessory dwelling unit.
If more parking must be added, it can be placed within the required setbacks. Tandem parking is allowed, unless otherwise restricted by special rules.

Additional Requirements in Carson
Most newly constructed ADUs must comply with California Title 24 Building and Energy Efficiency Standards. If you submitted your permit application later than January 1, 2020, this means you must provide solar panels on new ADUs to offset their reliance on the grid. This does not necessarily mean the solar panels need to be installedonthe ADU itself. They can be installed on the primary dwelling unit or a new or existing array.
Some exemptions may apply to certain ADUs. Possible exemptions include:
- A detached garage converted to an ADU.
- An ADU built wholly within or attached to the primary dwelling unit.
- Manufactured ADUs.
- ADUs with small or shaded roofs.
No, a separate electric and water meter is not required for an ADU. However, you may request one from the city.
Not necessarily. An ADUcanbe permitted under the existing address. If you want your ADU to have its own address, you can apply to the Mapping and Property Management Division (MPM) for a “½” address designation. In other words, if your address is 1234 Elm Street, your ADU could have a separate address of “1234½ Elm Street.”
Low Impact Development (LID) is an approach to land development or redevelopment that seeks to preserve and conserve onsite water quality and natural features, with minimal detrimental effect to local waterways and ecosystems. The City of Carson may require LID fees for larger ADUs.
Operating an ADU as an Airbnb or short-term rental is prohibited by the City of Carson.
Any ADU built within the last 15 years is exempt from rent control. The City of Carson limits rent increases to 3% per year for older, non-rent-controlled buildings. Newly-constructed ADUs are usually exempt.
You can use gas appliances in an ADU in the City of Carson as long as all building codes, safety standards, and installation guidelines are adhered to. The proper permits must be obtained, and requirements for safety and ventilation observed.
You are not required to put fire sprinklers in your ADU if the main dwelling unit is not required by law to have fire sprinklers.
Have Additional Questions?
Visit our comprehensive FAQ page for more information.